Assam Chief Minister Himanta Biswa Sarma and Adani Group Director Jeet Adani laid the foundation stone for a new thermal power plant in Dhubri district.
This massive 48,000 crore project is the largest single private industrial investment in the state. The plant is built at Chapar and will feature four units of 800 MW each, making a total capacity of 3,200 MW. Official reports confirm that the project aims to make Assam a surplus power producer by the early 2030s. Adani Power secured this project through a competitive bidding process on the
Ministry of Power DEEP portal in October 2025.
The facility will use ultra-supercritical technology to consume less coal and reduce emissions. The plant covers 585 hectares across several villages and will need rail-only transport for coal to protect the local environment. Observers can monitor further updates through filings on the
Ministry of Environment, Forest and Climate Change PARIVESH portal for the final environmental clearance letter.